City Planning Office head Janice Claire Canta, in a meeting of the Regional Development Council’s (RDC) infrastructure and utilities development committee, reiterated the local government’s call to proceed with the project.
“We want the RDC to
endorse this project again to the level of Cabinet secretary for very immediate
action, for the money to be downloaded, and for the project to be implemented
at the soonest possible time,” Canta said during Thursday’s meeting.
“It doesn’t matter to
us who implements it (so long) as the project is implemented the soonest.
Biddings have been done and all have been failures,” she added.
Two years ago, a
memorandum of agreement was signed by the Local Water Utilities Authority
(LWUA), National Housing Authority, Department of Public Works and Highways 8
(Eastern Visayas), Leyte Metropolitan Water District (LMWD), and Tacloban’s
city government, identifying and delineating the roles of each agency.
The PHP565-million
project will be undertaken in two phases and the permanent source of the water
supply would be the LMWD treatment plant in Tingib village in Pastrana, Leyte.
The budget has been available since 2014, said Canta.
In a consultation
meeting last Feb. 20, a representative of LWUA confirmed that the project
bidding had failed twice.
“With the delay, the
city government sent a letter to the Office of the President on Feb. 6,
providing details of historical contexts and some letters of complaint from
thousands of relocated families. It would be good if we have backing from RDC,”
Canta said.
RDC private sector
representative Tiburcio Morales wondered why the project has been delayed
despite President Rodrigo R. Duterte’s order to complete the permanent water
supply project.
“We have been
coordinating and monitoring and what are the results for four years? This, a
pain in the neck of the RDC. We have done our best, but the agencies concerned
have not done their best!” Morales added.
Medium- and long-term
water projects are being implemented by LWUA, a state-run corporation based in
Quezon City. LWUA has no office in the provinces.
The government
targets to move 14,000 families to the resettlement sites within the
year.
As of this month, about 10,000 families have already been transferred from danger zones to their new homes. (SQM/PNA)
As of this month, about 10,000 families have already been transferred from danger zones to their new homes. (SQM/PNA)