DPWH Eastern Visayas
Regional Director Edgar Tabacon admitted on Tuesday that the limited capacity
of contractors is a major setback to their goal to ensure timely completion of
projects.
“What else can we do
to increase our accomplishment rate if contractors have very limited capacity
to implement projects? Tabacon asked.
This year, the DPWH
regional office has invited contractors to attend trainings on conducting
surveys, preparing project designs, and making plans. These trainings were
originally designed for DPWH personnel, Tabacon said.
“The most challenging
part is the limited capacity of contractors. We have to help them improve on
some technical aspects of construction activities because they are so dependent
on us to comply some required documents,” Tabacon said.
He also asked local
contractors to buy equipment and hire more engineers in preparation for more
roads and bridges projects in 2019.
The DPWH regional
office and 13 district offices in Eastern Visayas proposed a PHP70 billion for
next year, more than double than the PHP32 billion approved outlay for 2018.
In 2017, the
infrastructure agency only attained 70 percent accomplishment with 233 projects
still ongoing. The completion rate is way below than the 85 percent annual
target.
In a press briefing
last January 27 in Davao City, President Rodrigo Duterte ordered DPWH
contractors to finish delayed projects in 30 days or face contracts
cancellation.
To ensure that there
will be no unfinished projects starting 2019, all projects will have an
implementation time frame of 300 days or less.
“Big projects will be
implemented by phase so that there would be unfinished project by the end of
every year,” Tabacon added.
The strategy is in
compliance to annual cash-based budget starting 2019. According to Memorandum No.
129 of the Department of Budget and Management, agencies can only incur
contractual obligations and disburse payments for goods delivered and services
rendered and inspected within the year, with an extended payment period of
three months.
This will effectively
limit agencies to submit budget proposals reflecting payment of goods and
services that will “actually be delivered for the year”, according to DBM.
This shift is
expected to quicken program delivery, as well as strengthen the “focus and
accountability of government” as target outputs of government programs become
more clearly linked to their appropriated budget. (SQM/PNA)