NAVAL, Biliran, June 23 --The PHP43 million
construction of Biliran Diversion Road project will resume its construction
activities after problem on Road-Right of-Way (RROW) has been settled.
This is revealed by Engr. David P. Adongay Jr.,
District Engineer of the Department of Public Works and Highways (DPWH)-
Biliran District Engineering Office (BDEO).
“We can now issue resume work order to the
contractor because the permit to enter was signed by the affected landowner,”
said Adongay.
According to Adongay, the construction of Biliran
Diversion road was hindered to proceed with the implementation because one of
the landowners affected in the road opening refused to sign the “Permit to
Enter”.
Ms. Edwina N.Tan, RROW agent, said the problem on
diversion road was settled by paying the affected landowner the exact amount as
computed based on the assessed value of his lot.
Engr. Albert Cañete, project engineer, said that
once the resume work orderwould be issued, contractor would be advised to
render over time work 24/7.
“The construction of Biliran Diversion Road at
Biliran, Biliran has accomplished 60 percent as of May 30, 2017 and if weather
condition is good, hopefully we can finish it by August or September this
year,” Cañete said.
The completion of the project will provide the
traveling public coming from cities of Tacloban, Ormoc and Baybay and from
other neighboring municipalities going to the northern and eastern part of
Biliran Province and vice versa in a much safer and faster transport of goods
and services and at a reduced travel time by 20 minutes. The population to be
served by the road ranges from 120,000 to 135,000, seven Municipalities and 50
barangays. (DPWH/BDEO-PR/PNA)