CARIGARA, Leyte, Sept. 29 (PNA) -- After a year of
widening and reconstruction activities, a vital bridge connecting a road that
links the two major cities in the province is now passable.
The Department of Public Works and Highways
formally opened this week the two lanes of Hiagsam Bridge located within the
highway that connects Tacloban City to Ormoc City and Biliran province.
“The bridge’s finishing touches is not yet done,
but we just opened half of it to ensure smooth traffic flow,” said Carlos
Veloso, district engineer of the DPWH Leyte 2nd engineering district.
The bridge costs PHP74 million funded through the
2015 calamity fund and regular budget of the DPWH this year.
The bridge was among those structured destroyed
during the onslaught of typhoon Seniang in December 2014.
The reconstructed bridge is said to be resilient to
flooding and earthquake.
The repair was delayed after the contractor asked
for extension to rebuild the bridge, pushing the completion date until this
month.
Veloso said that after the reconstruction of the
bridge last June, a second bridge has been constructed just beside the old one,
to complement the road widening project.
Key DPWH officials in the district led the
reopening of the bridge.(PNA)
JMC/SQM/LIZBETH ANN A. ABELLA/EGR