CARIGARA,
Leyte, July 1 (PNA) -– The Second Leyte Engineering District (2nd LED) of the
Department of Public Works and Highways (DPWH) based here reports that three of
its major projects started in 2015 now near completion and is right on target.
The
construction of the Civic Center in Tabontabon town, was funded under the
DILG’s Rehabilitation After Yolanda (RAY) Batch 2 fund worth PHP30 million.
The project
started on December 14, 2015 and target to be completed by August 24, 2016. It
is now 68 percent complete
.
Meanwhile,
the repair and improvement of a slope protection along the Palo-Carigara-Ormoc
Road was completed on May 26, 2016. The project which costs PHP9.27 million was
undertaken by Kauie Builders and construction supply.
The Mainit
Bridge along the Jaro-Dagami-Burauen-Lapaz road is now reported to be 85
percent complete. Project cost was pegged at PHP14.49 million and was funded
under the disaster related and emergency rehabilitation fund in 2015.
Mainit
Bridge was among the number of bridges that was destroyed during the onslaught
of Typhoon Senyang in December 2014. The project is targeted to be completed
this July.
This as
among the priority project by the 2nd LED for 2016 is the repair and
rehabilitation of 18 bridges. Most of bridge within the area are either old or
have been damaged by heavy rains and water flow during the past typhoons
2nd LED
District Engineer Carlos Veloso said this year funds of the district engineering
officer will be used for the construction of bridges, maintenance and
rehabilitation of major highways and completion of primary projects.
FFC/SQM/AHLETTE C. REYES/EGR