TACLOBAN
CITY, July 29 (PNA) -– Half lane in the ongoing reconstruction of the vital
Hiagsam Bridge along the Palo-Carigara-Ormoc national highway is now completed,
prodding the Second Leyte Engineering District of the Department of Public
Works and Highways (DPWH 2nd LED) to declare the first phase of the bridge
project to be completed by August.
The target
date of completion was this July; however, driving its huge pier deep down into
soil caused additional days of work including the soil exploration and boring
test conducted prior to the actual construction.
Presently,
the DPWH 2nd LED reports the bridge to be 83 percent complete, with half of the
lane of the main bridge already poured with concrete, while the other half will
be completed soon.
DPWH 2nd LED
District Engineer Carlos Veloso said this just forms part of the first phase of
the project as the new bridge will have a total of four lanes to accommodate
increasing traffic.
The Hiagsam
Bridge is a reinforced concrete deck girder (RCDG) bridge which is 19.3 meters
wide and will span the length of 50.8 meters. The bridge will be expanded on
each side in line with the road widening projects being done to highways
adjacent to the bridge.
The bridge
was damaged during typhoon Senyang in 2014 and formal works on the bridge
commenced on November 16, 2015. The bridge reconstruction runs on a PHP37.9
million budget.
Other
improvement works will also be done on the bridge such as slope protection,
drainage and sidewalks.
Construction
is being done by MWJ Construction through the supervision of the DPWH 2nd LED.
An asphalt
overlay detour spillway has been constructed as an alternative bridge and has
since been utilized to provide access along this route. The detour bridge is
accessible to motorcycle, light vehicles and medium truck. The detour bridge
runs both ways. (PNA)
LAP/SQM/AHLETTE C. REYES/EGR
LAP/SQM/AHLETTE C. REYES/EGR
No comments:
Post a Comment